Showing posts with label Measurement. Show all posts
Showing posts with label Measurement. Show all posts

Monday, August 14, 2017

QUALITY CONTROL MEASURES AT SITE

QUALITY CONTROL
MEASURES AT SITE

Study duties responsibilities, Tender specification, standards, codes of practice and work instruction.

Evolve effective acceptance/rejection procedures for construction materials in coordination with the project purchase department.

Do proper sampling and testing of steel, cement, concrete, aggregates, water, etc., and verify test results in view of standards and work specifications prior to their use in construction. Also control quality of electrodes to their use in welding.

Set procedures to control quality at the points of storage for raw materials, mixing and placing of concrete.

Follow the prescribed curing and deshuttering schedules.

Observe procedures to control quality of welded joints of structural steel members.

Evolve a system to check quality of workmanship in all construction activities.

Keep all revised Indian Standards and codes of practice available in QC laboratory and have them handy during discussion with client/consultant.

Maintain sequence of construction required under any activity.

Discuss QA/QC issues as a separate agenda during site review meetings with staff.

Observe regular schedule for maintenance, repairs and calibration of plants and equipments.

Keep spare parts/materials for laboratory equipments weigh batchers, batching plant, etc., always keep spare vibrators ready at site.

Carry work instruction cards in pocket while supervising/inspecting works.

Regularly maintain the formats prescribed under ISO 9002 Quality assurance system

Practice sound house keeping methods to achieve saving, safety and quality.

Sunday, August 6, 2017

What is Analysis of Rates or Rate Analysis of Civil Works?


What is Analysis of Rates or Rate Analysis of Civil Works?

Every construction project is divided into number of activities. Each activity consists of different types of civil or construction works. For example, the in the construction of a building, the activities can be excavation or earthwork, Concrete work, masonry work, Wood work such as doors and windows, plumbing, flooring, waterproofing, finishing work such as plastering, painting or distempering.

The Activity earthwork can be divided into many types based on depth and type of soil. For example, an excavation of 1.5m deep in soft soil, an excavation of 3m deep in hard soil. Likewise, concrete work can be divided into many types based on its mix proportions and its placement. For example, M25 reinforced concrete work in foundation, M30 reinforced concrete work in columns, slabs etc. Likewise, there can be many small civil works in every construction project.

The cost of any construction project is calculated based on each works associated with every construction activity. Thus it is essential to calculate cost of each small works.

Rate analysis of Civil Works or Building Works is the determination of cost of each construction work per unit quantity. This cost includes the cost of materials, labours, machinery, contractors profit and other miscellaneous petty expenses required for the particular work to be complete in unit quantity. For example, cost of 1 cubic meter of M20 RCC work in slab, Cost of 1 cubic meter of excavation in soft soil of 1.5m depth, cost of 1 square meter of plastering of 20mm, cost of 1 square meter of painting work with specified paint in 2 layers or 3 layers as required.

The cost of materials in rate analysis is calculated as combination of cost of material at origin, its transportation costs, taxes. The rate of labour is based on skill of the labour, such as skilled labour, semi-skilled and unskilled labour. The cost of materials and labours vary from place to place. Thus, the cost of each construction work varies from place to place.

What are the factors affecting Analysis of Rates of Civil Works?

Factors which affect the rate analysis of civil works are:

Specification of the civil work and materials such as quality of materials, proportion of mortar or concrete, thickness of plastering, number of coats of painting, depth of excavation, type of soil etc.Location of the construction site – Distance of construction site from source of materials, availability of labours, availability of water, machinery etc. influence the rate analysis of construction work.Quantity of materials, number of different types of labours and rates of materials and labours influence the rate analysis.Profit of the contractor, miscellaneous expenses and other overheads also influence the rate analysis.

What are the elements of Rate Analysis of Civil Works?

Elements which constitute the rate analysis are:

a) Material cost inclusive of wastage
b) Labour cost
c) Plant & machinery owning and operating charges
d) Water charges
e) Taxes
f) Insurance/ risk coverage charges
g) Contractor’s overheads and profit

Why Analysis of rates is required in construction projects?

The rate analysis may be required in construction projects for following purposes:

For the purpose of tendering. In the case of tendering, the contractor may calculate cost of unit work involved in each construction activity for justified quoting of rates. The client may also require rate analysis to calculate the cost of construction project.To assess the requirements of quantities of labours, materials, machineries and capital to complete the project.To optimise the use of labour, materials and machineries and to know the alternatives to optimize the resources.To assess the rate of unit work from time to time for payment increase in material or labour costs or any deviations in work specifications, extra items of work to the contractor.To compare the cost of project with the sanctioned capital of the project to take necessary action or regularization of excess or less cost.To workout the budget of the construction project and control the cash flows at various stages of construction work.To find out the irrational rates quoted by the contractors during tendering process.To serve as the basic data in case of dispute among project owner and contractor.

Tuesday, June 6, 2017

Project Estimating and Cost Management


Many of the currently available books on estimating cover project estimating in a discipline-specific mode, such as construction estimating, software development estimating, and process plant estimating. Although there is a great deal of commonality in estimating techniques among all industries, distilling the nondiscipline-specific topics is sometimes difficult because they tend to get masked by the details of the discipline that is the subject of the project.

Monday, May 16, 2016

Unit of Formwork Measurement

Formworks are measured in terms of area. So any unit such as square meter, square foot, square centimetre can be adopted. But generally, square meter and square foot of the contact area with concrete is taken as the unit of measurement. The dimensions of a formwork should be measure correct to the centimetre or inches whichever the case may be.

Formworks are measured as just contact area, not area of formwork, as shown below:

Saturday, April 30, 2016

Units of measurement

The International System S.I. of units is used. The primary units are the following: